|
The Sebastian Inlet jetty is now nearly 80 years old. Although it has been refurbished and extended over the years, it is now considered unsafe in spots. The last 80 feet of the pier has been closed since Hurricane Floyd wreaked havoc on the East Coast in Fall of 1999. |
| Prepared for: Florida Department of Environmental Protection Division of Recreation and Parks Bureau of Design and Recreation Services |
Prepared by: Bridge Design Associates, Inc. PO Box 210173 West Palm Beach, FL 33421-0173 |
Scope of Services
Bridge Design Associates, Inc. was retained to review the available information regarding the existing North Jetty Fishing Pier, and to recommend possible alternatives to repair or replace the existing structure, and determine probable costs of construction for the various options.
Evaluation and Options
Bridge Design Associates, Inc. has reviewed an extensive report prepared for the Sebastian Inlet Tax District by Underwater Engineering Inspection and Specialty Services and an additional report prepared for Florida Department of Environmental Protection by David C. Jones, P.E. Both reports identify critical amounts of deterioration of the existing foundation piling, crib piling, and superstructure components including the concrete supporting beams and metal grating for the crib deck openings.
Based on the information contained in these reports, the conclusion was to minimize the use of the existing pier superstructure and explore options which could minimize the disruption of the existing crib portion of the jetty but create a safe platform for recreation on the fishing pier.
The initial focus has been on three options:
| Option One | Remove the existing fishing superstructure and replace it with a new structure. |
| Option Two | Remove portions of the existing superstructure and integrate the remaining portions into the new structure. |
| Option Three | Construct a new structure around the existing structure minimizing demolition of the existing structure as much as possible. |
Findings
In Option One, the existing superstructure including the beam, grating and handrails would be removed. The vertical crib piling and southern side batter piles would be saw cut to the top of the existing rock rubble in the crib and adjacent to the batter piles. The demolition process would have to start at the easternmost end of the jetty and progress westerly. The contractor could chose to remove portions of the jetty from the water utilizing barges, but the work schedule would be dictated by ocean conditions. It is anticipated that the contractor would have to secure the existing structure enough to place a crane on the existing structure to aid in the demolition. Once the existing structure is removed, the contractor could begin the rebuilding process work from the western section and progress easterly. In order to install the new substructure piling, some of the existing slope and rock rubble would have to be temporarily relocated. This process would have to be done in relatively small increments in order to maintain the integrity of the jetty crib. Once the new piling and superstructure are completed, additional stone would have to be added to the crib due to the proposed increased width.
Option Two
The thought process for Option Two was to remove only the superstructure beams, grating, and handrails. The existing piles would be left in place. During the review of this option with contractors, they viewed Options One and Two as essentially the same. The major difference was only where they were required to cut the existing piling, at the top near the superstructure or at the rock rubble line. The additional piling debris was negligible in the cost analysis. The description of the building process is basically the same as Option One.
Option Three
The focus of Option Three was to eliminate as much of the demolition as possible. By reducing the demolition, three items were accomplished. The crib and jetty remain in stable condition with little risk to the integrity during the construction process. The time to construct would be reduced by at least one-third. An there would be a substantial cost savings. In Option Three, the contractors anticipate constructing the new pier from itself which eliminates the need to secure the existing structure.
Recommendations
In all of the proposed options, the pier deck area has been increased from 16' 6" to 21' 4" which will provide a safer useable area for the fishermen. Option Three, because of the reduced cost and less disruption to the existing jetty, would appear to be the best option.
On October 5, 2000 I was lucky enough to be present (with a digital camera!) when the FIT weather station was being serviced.
The last 11 grates at the end of the jetty are no longer present.
Careful--watch your step!
Currently, the rocks extend out past the end of the pier area. This
helps to break up some of the wave action before it reaches the structure.
However, I have seen waves breaking on the end of the jetty also.
Lots of fishermen in boats surround the tip of the jetty.
Looking down from the top of the weather station, I saw lots of bait fish--and
even a manatee or two!
The tidal plume was exceptionally visible. The murkier, brownish water
is from the Indian River Lagoon.
Tannins from trees growing in and near the brackish water causes this coloration.
Whoa! Don't look down! As Maria said "If it falls over, I guess
we go down." Very reassuring!
Monster Shoals--waves don't break in a hole! A few hours later, the
waves were beautiful out there!
Inside Monster Shoals, south side of the inlet. Now, I think maybe
the Hole is in this area--it is deeper, a fishy pit.
Sebastian's South Inlet Jetty--many people venture off the pier structure
and onto the rocks.
Also, on both sides of the bridge there is a catwalk for the public's enjoyment!
It's hard to tell now, but this is the way the inlet used to run.
These local rocks came from a rock shelf near Cocoa (thus the name Rockledge!)
No one but a surfer would believe me, but there are more surfers in the water
today than fishermen on the jetty!
OK, one last pan arround...